Tiers
|
|
=====
|
|
.. index Tiers
|
|
|
|
RTEMS has a tiered structure for architecture and BSPs. It provides:
|
|
|
|
#. A way to determine the state of a BSP in RTEMS.
|
|
|
|
#. A quaility measure for changes entering the RTEMS source code.
|
|
|
|
The RTEMS project supports RTEMS Architecture Tiers. Each architecture
|
|
resided in one of the numbered tiers. The tiers are number 1 to 4 where
|
|
Tier 1 is the highest tier and Tier 4 is the lowest. Architectures move
|
|
between tiers based on the level of support and the level of testing that
|
|
is performed. An architecture requires continual testing and reporting
|
|
of test results to maintain a tier level. The RTEMS Project's continuous
|
|
integration testing program` continually monitors and reports the test
|
|
results.
|
|
|
|
The RTEMS Architecture Tier system provides a defined way to determine
|
|
the state of an architecture in RTEMS. Architectures age and support
|
|
for them drops off and the RTEMS Project needs a way to determine
|
|
if an architecture should stay and be supported or depreciated and
|
|
removed. The tier system also provides users with a clear understanding of
|
|
the state of an architecture in RTEMS, often useful when deciding on
|
|
a processor for a new project. It can also let a user know the RTEMS
|
|
Project needs support to maintain a specific architecture. Access to
|
|
hardware to perform testing is a large and complex undertaking and the
|
|
RTEMS Project is always looking for user support and help. If you can
|
|
help please contact someone and let us know.
|
|
|
|
The tier structure in RTEMS is support by the Buildbot continuous integration
|
|
server. Changes to RTEMS are automatically built and tested and the results
|
|
indicate if a BSP currently meets its tier status. As the RTEMS Project
|
|
does not own hardware for every BSP, it is critical that users provide
|
|
test results on hardware of interest.
|
|
|
|
The rules for Tiers are:
|
|
|
|
#. A BSP can only be in one of the following tiers:
|
|
|
|
+------+-----------------------------------------------------------------+
|
|
| Tier | Description |
|
|
+------+-----------------------------------------------------------------+
|
|
| 1 | * The RTEMS Kernel must build without error. |
|
|
| | * Tests are run on target hardware. |
|
|
+------+-----------------------------------------------------------------+
|
|
| 2 | * The RTEMS Kernel must build without error. |
|
|
| | * Tests can be run on simulation. |
|
|
+------+-----------------------------------------------------------------+
|
|
| 3 | * The RTEMS Kernel must build without error. |
|
|
| | * There are no test results. |
|
|
+------+-----------------------------------------------------------------+
|
|
| 4 | * The RTEMS Kernel does not build. |
|
|
+------+-----------------------------------------------------------------+
|
|
| 5 | * The BSP is to be removed after the next release. |
|
|
+------+-----------------------------------------------------------------+
|
|
|
|
#. An architecuture's tier is set by the highest BSP tier reached.
|
|
|
|
#. The tier level for a BSP is set by the RTEMS Project team. Movement of BSP
|
|
between tier level requires agreement. The Buildbot results indicate the
|
|
minimum current tier level.
|
|
|
|
#. Changes to RTEMS may result in a BSP not meeting its tier are acceptable if
|
|
the change is accompanied by an announcement and a plan on how this is to be
|
|
resolved. Temporary drops in tier are expected and should be brief.
|
|
|
|
#. Test results are set on a per BSP basis by the RTEMS Project team. Changes
|
|
to the test result values requires agreement. The test results are defined
|
|
as:
|
|
|
|
#. Passes
|
|
|
|
#. Expected Failures
|
|
|
|
Expected failures must be explicitly listed. A BSP is required to have a
|
|
valid test result entry on target hardware to reach tier 1.
|